September 11, 2008

GOLDREA TERMINATES DAYE ACQUISITION
greater benefit by continuing to expand the existing gold resources it has developed to date on its 65,000 hectares of exploration licenses in Shandong Province, China...

August 28, 2008

GOLDEN ROSE PRODUCTION BEGINS
3,150 tonnes of material has been stock piled... work will continue until 20,000 tonnes has been made available... company has received its updated NI 43-101 qualifying, Mineral Resource Estimate, and Preliminary Economic Analysis...

March 12, 2008

GOLDEN ROSE STOPING EXPECTED
Crosscutting commenced to access the ore discovered in Hole GZK810, stoping should begin within the month...

December 4, 2007

PROGRESS REPORT ON CHINA GOLD PROJECT
Golden Rose Shaft – Surface plant construction is ongoing... 35% complete. Ludi Joint Venture with 3rd Brigade (70% GOR, 30% 3rd Brigade) – Final approval is expected from the government by mid December 2007. Daye Mine - Acquisition of an 80% interest in the operating Daye Gold Mine (1750 TPD) is still on track to be completed in February 2008.

November 2, 2007

DAYE ACQUISITION STATUS UPDATE
application for approval of the Daye Acquisition is moving smoothly through the final steps of the process required by the Central Government of the People’s Republic of China...

October 11, 2007

TIANZIA ZONE EXTENDED 600 METRES
Holes GZK758 and 760 are new discoveries 600 meters down dip from the West Tianjia mineralization mapped on surface...

August 23, 2007

CHINA DAYE MINE UPDATE
The Daye Mine acquisition is progressing favorably... a strong possibility... Central Government approval will not be required... Drilling continues with two drill machines working full time on the Daye Property...
在中国山东收购大业金矿最新进展 more >>

June 11, 2007

DRILLING CONTINUES AT DAYE
Drilling continues on the Langjiazhoung and Majiakuang properties on the Rushan Goldrea Gold J.V., in Shandong China...

April 26, 2007

DAYE GOLD MINE ACQUISITION
Goldrea Resources Corp. entered into an agreement with Rushan Guoxin Assets Management Ltd...

April 4, 2007

PRELIMINARY EVALUATION REPORT - NI 43-101
Exploration and Development Joint Venture, between Goldrea Resources Corp and China Shandong #3 Mineral & Geological Exploration Institute (The 3rd Brigade)...

March 21, 2007

PROGRESS REPORT & RESOURCE ANALYSIS - NI 43-101
Rushan Goldrea Gold Inc. Joint Venture Mineral Exploration Project...

March 21, 2007

UPDATE ON DAYE MINE ACQUISTION AND HISTORICAL REVIEW
Daye Gold Mine is an operating 1750 TPD gold mine which produced approximately 65,000 ounces...

January 19, 2007

NI 43-101 INDICATES 331,175 OUNCES
The company has completed 20,200 metres (66,256 feet) of exploration diamond drilling in 83 holes...

December 7, 2006

GOLDREA APPOINTS CHIEF OPERATING OFFICER FOR CHINA
Previous to his recent work in China, Mr. Blair worked in various management capacities in North, Central and South America...

November 10, 2006

GOLDREA COMPLETES PURCHASE AGREEMENT FOR DAYE GOLD MINE
Goldrea has completed considerable exploration drilling and have identified considerable gold mineralization...

August 23, 2006

GOLDREA FOCUSING ON CHINA PRODUCTION GROWTH
Has signed an engagement agreement with Tortuga Merchants to further develop and execute Goldrea's China business...

October 26, 2006

GOLDREA/TORTUGA OUTLINE STRATEGIC PLAN FOR CHINA
Over the next 24 months we expect to move on completing three to four acquisitions of producing mines in China...

October 13, 2006

DEFINITION DRILLING CONTINUES TO EXTEND THE JINGKOU ZONE
The Jingkou Zone now has eight drill holes, three surface trenches, and a shallow exploration shaft confirming...

July 6, 2006

NEW EXPLORATION LICENSES ARE NEGOTIATED BY GOLDREA
The WeiHai Agreement includes eight exploration licenses covering 90 square kiometres south and west of...

June 2, 2006

NEW GOLD ZONE DISCOVERED AT DONGJINGKOU
The latest drilling on the Daye property has intersected mineralization on a new shoot atthe western end...

May 23, 2006

WARDROP CONTRACTED FOR DAYE MINE TECHNICAL REPORT
The Company has completed translation of the Daye Gold Mine Assets, sericite operations (25%)...

May 1, 2006

EXPLORATION SHAFT COMMENCED ON THE DOWN DIP EXTENSION OF THE DAYE GOLD MINE OREBODY
The Company has commenced driving a 300 metre shaft on the down dip extensions of the Daye orebody...

March 23, 2006

INTERIM REPORT ON THE TRENCHING AND DRILLING DAYE GOLD MINE
The surface exploration is presentely focused on the western extensions of the gold sulphide mineralization...

March 3, 2006

MOBILIZATION OF SHAFT DRIVING EQUIPMENT HAS BEGUN
This shaft will allow for lateral development along strike and provide drill access for definition drilling...

February 12, 2006

MINERAL RESOURCE EVALUATION REPORT COMPLETED
Exploration drilling by Goldrea has identified several favourable intersections on the down-dip extensions...

January 12, 2006

POTENTIAL PURCHASE OF OPERATING DAYE GOLD MINE - CHINA
The Company has entered into a Letter of Intent with Rushan City to purchase up to 100% interest in their operating...

December 21, 2005

150,000 TONNE BULK TEST PROPOSED AND DIAMOND DRILL UPDATE
The next phase of the exploration work at Daye will include a bulk sampling program designed to mine 150,000 tonnes of...

October 14, 2005

JOINT VENTURE UPDATE FROM GOLDREA'S CHINA RUSHAN PROJECT
The Company's Joint Venture property surrounds the China Rushan gold mine and includes the rights to ore below...

August 15, 2005

JOINT VENTURE UPDATE FROM GOLDREA'S RUSHAN PROJECT CHINA
Currently the Company is conducting trenching and drilling along strike to the west of the open pit...

July 11, 2005

EXPLORATION UPDATE FROM GOLDREA'S RUSHAN PROJECT CHINA
The drill program was laid out with wide spaced holes to trest the extensions both laterally and down dip...

March 4, 2005

RESULTS EXTEND MINERALIZED ZONE UP TO 500 METRES DOWNDIP FROM DAYE OPEN-PIT
Rushan Goldrea Gold Inc. have resumed drilling on their Daye Property, City of Rushan...

January 17, 2005

DRILLING COMMENCES IN SHANDONG PROVINCE, CHINA PROPERTY
The drilling contract has been awarded to the #3 Brigade in Shandong Province for approximately CDN$35.00 per metre...

September 17, 2004

BUSINESS LICENSE GRANTED FOR SHANDONG PROVINCE CHINA
congratulations are extended to Mr. Richard Shao, the officials of China Rushan Daye Gold Mine and officals of Rushan City for their diligence in expediting the permits and business license which began in early April 2004...

August 13, 2004

CHINA CENTRAL GOVERNMENT APPROVAL RECEIVED
applied for their business license from Rushan City...

June 16, 2004

GOLDREA GETS BREAK IN CHINA JOINT VENTURE AND BUSINESS LICENSE UPDATE
cooperative joint venture... has been approved by the Municipal and Provincial Government of China subject to...

March 30, 2004

GOLDREA COMPLETES COOPERATIVE JOINT VENTURE WITH RUSHAN CITY
includes all exploration on the Rushan Property, up to the limits of the existing open pit as well as below the existing pit starting at the 150 metre level...

January 6, 2004

CHINESE GOLD PROPERTY ASSIGNMENT AGREEMENT COMPLETED
with MSC Pioneer Holdings limited... for 100% of their joint venture interest in 65,000 hectares of exploration licenses...